Job Shop Scheduling Problem for Machine Shop with Shifting Heuristic Bottleneck

Article ID

ZE6CO

Job Shop Scheduling Problem for Machine Shop with Shifting Heuristic Bottleneck

Jilcha Kassu
Jilcha Kassu
Berhan Eshetie
Berhan Eshetie
DOI

Abstract

Job shop scheduling is an Np-Hard combinatory in the field of scheduling problem. Due to this reason, Dejena Aviation Industry (DAVI) has faced a problem to determine the optimum sequences of jobs on machines that can optimize the makespan. The purpose of this study is therefore, to minimize the makespan of the job shop production system of DAVI production system using shifting bottleneck algorithm. Secondary data was collected from the production log book five machines were considered during the production of five jobs. The findings of the shifting bottleneck algorithms showed that an 8.33% reduction in the total makespan of the company job shop production system. Moreover; machine one (41%) and three (36%) are found to be least utilized machines whereas machine three (64%) and five (59%) are relatively the busiest machines.

Job Shop Scheduling Problem for Machine Shop with Shifting Heuristic Bottleneck

Job shop scheduling is an Np-Hard combinatory in the field of scheduling problem. Due to this reason, Dejena Aviation Industry (DAVI) has faced a problem to determine the optimum sequences of jobs on machines that can optimize the makespan. The purpose of this study is therefore, to minimize the makespan of the job shop production system of DAVI production system using shifting bottleneck algorithm. Secondary data was collected from the production log book five machines were considered during the production of five jobs. The findings of the shifting bottleneck algorithms showed that an 8.33% reduction in the total makespan of the company job shop production system. Moreover; machine one (41%) and three (36%) are found to be least utilized machines whereas machine three (64%) and five (59%) are relatively the busiest machines.

Jilcha Kassu
Jilcha Kassu
Berhan Eshetie
Berhan Eshetie

No Figures found in article.

Kassu Jilcha. 2015. “. Global Journal of Research in Engineering – J: General Engineering GJRE-J Volume 15 (GJRE Volume 15 Issue J1): .

Download Citation

Journal Specifications

Crossref Journal DOI 10.17406/gjre

Print ISSN 0975-5861

e-ISSN 2249-4596

Classification
GJRE-J Classification: FOR Code: 091599
Keywords
Article Matrices
Total Views: 4257
Total Downloads: 2058
2026 Trends
Research Identity (RIN)
Related Research
Our website is actively being updated, and changes may occur frequently. Please clear your browser cache if needed. For feedback or error reporting, please email [email protected]

Request Access

Please fill out the form below to request access to this research paper. Your request will be reviewed by the editorial or author team.
X

Quote and Order Details

Contact Person

Invoice Address

Notes or Comments

This is the heading

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

High-quality academic research articles on global topics and journals.

Job Shop Scheduling Problem for Machine Shop with Shifting Heuristic Bottleneck

Jilcha Kassu
Jilcha Kassu
Berhan Eshetie
Berhan Eshetie

Research Journals