Reduction of Production Lead Time using Value Stream Mapping (VSM) Technique

α
Mirza Md. Sayeed Hasan
Mirza Md. Sayeed Hasan
α Rajshahi University of Engineering and Technology

Send Message

To: Author

Reduction of Production Lead Time using Value Stream Mapping (VSM) Technique

Article Fingerprint

ReserarchID

403N8

Reduction of Production Lead Time using Value Stream Mapping (VSM) Technique Banner

AI TAKEAWAY

Connecting with the Eternal Ground
  • English
  • Afrikaans
  • Albanian
  • Amharic
  • Arabic
  • Armenian
  • Azerbaijani
  • Basque
  • Belarusian
  • Bengali
  • Bosnian
  • Bulgarian
  • Catalan
  • Cebuano
  • Chichewa
  • Chinese (Simplified)
  • Chinese (Traditional)
  • Corsican
  • Croatian
  • Czech
  • Danish
  • Dutch
  • Esperanto
  • Estonian
  • Filipino
  • Finnish
  • French
  • Frisian
  • Galician
  • Georgian
  • German
  • Greek
  • Gujarati
  • Haitian Creole
  • Hausa
  • Hawaiian
  • Hebrew
  • Hindi
  • Hmong
  • Hungarian
  • Icelandic
  • Igbo
  • Indonesian
  • Irish
  • Italian
  • Japanese
  • Javanese
  • Kannada
  • Kazakh
  • Khmer
  • Korean
  • Kurdish (Kurmanji)
  • Kyrgyz
  • Lao
  • Latin
  • Latvian
  • Lithuanian
  • Luxembourgish
  • Macedonian
  • Malagasy
  • Malay
  • Malayalam
  • Maltese
  • Maori
  • Marathi
  • Mongolian
  • Myanmar (Burmese)
  • Nepali
  • Norwegian
  • Pashto
  • Persian
  • Polish
  • Portuguese
  • Punjabi
  • Romanian
  • Russian
  • Samoan
  • Scots Gaelic
  • Serbian
  • Sesotho
  • Shona
  • Sindhi
  • Sinhala
  • Slovak
  • Slovenian
  • Somali
  • Spanish
  • Sundanese
  • Swahili
  • Swedish
  • Tajik
  • Tamil
  • Telugu
  • Thai
  • Turkish
  • Ukrainian
  • Urdu
  • Uzbek
  • Vietnamese
  • Welsh
  • Xhosa
  • Yiddish
  • Yoruba
  • Zulu

Abstract

Value Stream Mapping (VSM) is a special type of flow chart that uses symbols known as “the language of Lean” to depict and improve the flow of inventory. In this research, process time and other unnecessary non value added activities of a battery manufacturing company have been reduced by using various lean manufacturing tools. The current situation is analyzed by showing a current state map. Then after using several lean tools, a future state value stream map has been showed. A different layout of the industry especially assembly section has been suggested. The layout of the assembly section is time wasting in current situation. They could reduce their overall production lead time as well as wastes by considering the suggestions about using lean tools and improved layout.

References

24 Cites in Article
  1. W Apel,J Li,Walton (2007). Value Stream Mapping For Lean Manufacturing Implementation.
  2. M Corrie (2004). Lean Success In An Admin-Istration Environment.
  3. Epe Dale (2002). Lean Enterprise: Minnesota Showcase.
  4. Mark Graban,John Toussaint (2011). Lean Hospitals.
  5. Imep (2003). Principles Of Lean Manufacturing With Live Simulation (Participant Workbook).
  6. M Jenkins (2002). PROCESS PLANNING.
  7. C Lacroix (2009). Understanding The Difference Between Mrp And Erp System.
  8. X Li (2014). A Literature Review On Value Stream Mapping With A Case Study Of Applying Value Stream Mapping On Research Process.
  9. D Locher (2008). Value Stream Mapping For Lean Development: A How-To Guide For Streamlining Time To Market.
  10. Karen Martin,Mike Osterling (2013). Value Stream Mapping: How To Visualize Work And Align Leadership For Organizational Transformation.
  11. R Moore,L Scheinkopf (1998). Theory of Constraints and Lean Manufacturing: Friends or Foes?.
  12. R Muther (1955). Methods of Plant Breeding, 2nd Edition.
  13. G Narayanan (2011). The "5S" Philosophy.
  14. N Pandhi,Singh,S Singh (2015). Unknown Title.
  15. M Poppendieck (2002). The Principles Of Lean Thinking.
  16. M Rother,J Shook (2003). From the Forward By John Shook and Dan Jones.
  17. M Rother,J Shook (2003). Learning to See -Value Stream Mapping to Create Value and Eliminate Muda.
  18. Mike Rother (2009). Toyota Kata.
  19. M Samad,Saifulalamand,Nishattusnim (2013). Value Stream Mapping To Reduce Manufacturing Lead Time In A Semi-Automated Factory.
  20. C Scodaniibbiio (2004). The road to Lean Manufacturing through the Value Stream Mapping.
  21. J Tinoco (2004). Implementation of Lean Manufacturing.
  22. L Tonkin (2004). Lear Office: Mapping Your Way to Change.
  23. H Wan,F Chen (2007). Leanness Score of Value Stream Maps.
  24. J Womack,D Jones (2003). Lean Thinking—Banish Waste and Create Wealth in your Corporation.

Funding

No external funding was declared for this work.

Conflict of Interest

The authors declare no conflict of interest.

Ethical Approval

No ethics committee approval was required for this article type.

Data Availability

Not applicable for this article.

How to Cite This Article

Mirza Md. Sayeed Hasan. 2017. \u201cReduction of Production Lead Time using Value Stream Mapping (VSM) Technique\u201d. Global Journal of Research in Engineering - A : Mechanical & Mechanics GJRE-A Volume 17 (GJRE Volume 17 Issue A1): .

Download Citation

Journal Specifications

Crossref Journal DOI 10.17406/gjre

Print ISSN 0975-5861

e-ISSN 2249-4596

Keywords
Classification
GJRE-A Classification: FOR Code: 091399
Version of record

v1.2

Issue date

July 11, 2017

Language
en
Experiance in AR

Explore published articles in an immersive Augmented Reality environment. Our platform converts research papers into interactive 3D books, allowing readers to view and interact with content using AR and VR compatible devices.

Read in 3D

Your published article is automatically converted into a realistic 3D book. Flip through pages and read research papers in a more engaging and interactive format.

Article Matrices
Total Views: 3540
Total Downloads: 1757
2026 Trends
Related Research

Published Article

Value Stream Mapping (VSM) is a special type of flow chart that uses symbols known as “the language of Lean” to depict and improve the flow of inventory. In this research, process time and other unnecessary non value added activities of a battery manufacturing company have been reduced by using various lean manufacturing tools. The current situation is analyzed by showing a current state map. Then after using several lean tools, a future state value stream map has been showed. A different layout of the industry especially assembly section has been suggested. The layout of the assembly section is time wasting in current situation. They could reduce their overall production lead time as well as wastes by considering the suggestions about using lean tools and improved layout.

Our website is actively being updated, and changes may occur frequently. Please clear your browser cache if needed. For feedback or error reporting, please email [email protected]

Request Access

Please fill out the form below to request access to this research paper. Your request will be reviewed by the editorial or author team.
X

Quote and Order Details

Contact Person

Invoice Address

Notes or Comments

This is the heading

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

High-quality academic research articles on global topics and journals.

Reduction of Production Lead Time using Value Stream Mapping (VSM) Technique

Mirza Md. Sayeed Hasan
Mirza Md. Sayeed Hasan Rajshahi University of Engineering and Technology

Research Journals