The Economic Development of Dam Construction Projects by Applying a Critical Chain Project Management

α
Mohammad Javad Khosravi
Mohammad Javad Khosravi
α Islamic Azad University, Tehran Islamic Azad University, Tehran

Send Message

To: Author

The Economic Development of Dam Construction Projects by Applying a Critical Chain Project Management

Article Fingerprint

ReserarchID

S98DF

The Economic Development of Dam Construction Projects by Applying a Critical Chain Project Management Banner

AI TAKEAWAY

Connecting with the Eternal Ground
  • English
  • Afrikaans
  • Albanian
  • Amharic
  • Arabic
  • Armenian
  • Azerbaijani
  • Basque
  • Belarusian
  • Bengali
  • Bosnian
  • Bulgarian
  • Catalan
  • Cebuano
  • Chichewa
  • Chinese (Simplified)
  • Chinese (Traditional)
  • Corsican
  • Croatian
  • Czech
  • Danish
  • Dutch
  • Esperanto
  • Estonian
  • Filipino
  • Finnish
  • French
  • Frisian
  • Galician
  • Georgian
  • German
  • Greek
  • Gujarati
  • Haitian Creole
  • Hausa
  • Hawaiian
  • Hebrew
  • Hindi
  • Hmong
  • Hungarian
  • Icelandic
  • Igbo
  • Indonesian
  • Irish
  • Italian
  • Japanese
  • Javanese
  • Kannada
  • Kazakh
  • Khmer
  • Korean
  • Kurdish (Kurmanji)
  • Kyrgyz
  • Lao
  • Latin
  • Latvian
  • Lithuanian
  • Luxembourgish
  • Macedonian
  • Malagasy
  • Malay
  • Malayalam
  • Maltese
  • Maori
  • Marathi
  • Mongolian
  • Myanmar (Burmese)
  • Nepali
  • Norwegian
  • Pashto
  • Persian
  • Polish
  • Portuguese
  • Punjabi
  • Romanian
  • Russian
  • Samoan
  • Scots Gaelic
  • Serbian
  • Sesotho
  • Shona
  • Sindhi
  • Sinhala
  • Slovak
  • Slovenian
  • Somali
  • Spanish
  • Sundanese
  • Swahili
  • Swedish
  • Tajik
  • Tamil
  • Telugu
  • Thai
  • Turkish
  • Ukrainian
  • Urdu
  • Uzbek
  • Vietnamese
  • Welsh
  • Xhosa
  • Yiddish
  • Yoruba
  • Zulu

Abstract

The dam construction industry in Iran has always been considered as one of the country’s most important industries due to the lack of rainfall. To accomplish this, we need to properly manage the dam construction process. Traditional algorithms, such as the Critical Paths Methods (CPM) and Program Evaluation and Review Technique (PERT) have been used since ancient times to plan and control most of the projects, including dam construction projects. With traditional methods of project management, a large percentage of time and resources are often lost due to reasons such as the lack of prioritization, student syndrome, and bad multi-tasking. The Critical Chain Project Management (CCPM) is a method for project planning, with emphasis on the resources needed to carry out the project. In this research, which was done on the Kahir reservoir, the CPM method was first used and then analyzed by CCPM method. Using resource dependency, identifying and embedding project buffers and leveling resources in this study reduced the implementation time of the project for 27 days

References

23 Cites in Article
  1. M Heydari,M Sadeghian,M Moharrampour,A Shahiri Parsa (2013). Introduction to floodplain zoning simulation models through dimensional approach.
  2. M Salarian,Z Shokri,M Heydari (2014). Determination of the Best Model for Flood Flows in the Western Basin of Lake Urmia.
  3. A Shahiriparsa (2016). Floodplain Zoning Simulation by Using Hec-Ras And Cche2d Models in the Sungai Maka River.
  4. Fazlolahzade Sadati,S (2014). Water Yield Estimation in Polrudwatershed Based on Empirical Methods and Modelling in Geographic Information System (GIS).
  5. M Salarian (2015). Classification of Zayandehrud river basin water quality regarding agriculture, drinking, and industrial usage.
  6. M Sadeghian (2016). Evaporation estimates for two hydroelectric power plants reservoirs in the Tocantins river basin - Brazil.
  7. M Heydari,Faridah; Salarijazi,Meysam; Ahmadianfar,; Iman,Sadeghian (2018). Mohammad Sadegh Predicting the Amount of Fertilizers using Linear Programming for Agricultural Products from Optimum Cropping Pattern Authors.
  8. F Othman,M Sadeghian,I Azad (2012). Investigate the Potential and Limitations of Meta-heuristics Algorithms Applied in Reservoir Operation Systems.
  9. F Othman (2012). Preliminary Review of the Optimal Operation of Reservoir Systems using Common Calculation Methods.
  10. M Noori (2013). Multiobjective operation optimization of reservoirs using genetic algorithm (Case Study: Ostoor and Pirtaghi Reservoirs in Ghezel Ozan Watershed).
  11. Mohammad Heydari,Faridah Othman,Kourosh Qaderi (2015). Developing Optimal Reservoir Operation for Multiple and Multipurpose Reservoirs Using Mathematical Programming.
  12. M Sadeghian (2015). A Statistical Review Of The Most Cited Isi Papers In The Field Of Reservoir Operation.
  13. A Shahiriparsa (2015). Introduction to linear programming as a popular tool in optimal reservoir operation, a review.
  14. M Heydari,F Othman,M Noori (2016). Optimal Operation Of Multiple And Multi Purpose Reservoirs Systems Using Non-Dominated Sorting Genetic Algorithm (Nsga-Ii).
  15. Mohammad Heydari,Faridah Othman,Mahmood Taghieh (2016). Optimization of Multiple and Multipurpose Reservoir System Operations by Using Matrix Structure (Case Study: Karun and Dez Reservoir Dams).
  16. M Heydari,M Sadeghian,M Daneshkhah (2017). A comparison between the amount of reservoir sediment load prediction during design period and the operational period.
  17. F Othman (2012). Direct and Indirect Effects of Drought using the Function Analysis Systems Technique (FAST) Diagram.
  18. M Heydari,F Othman,M Noori (2013). A review of the Environmental Impact of Large Dams in Iran.
  19. F Othman (2013). A Study on Sedimentation in Sefidroud Dam by using Depth Evaluation and Comparing the Results with USBR and FAO methods.
  20. F Othman,Mohammad Sadegh,; Heydari,Mohammad Sohrabi (2013). Mir Saeid Prediction of Water Level And Salinity of Lakes By using Artificial Neural Networks, Case Study: Lake Uremia.
  21. F Othman (2014). Review for "A Systematic Approach to the Histologic Evaluation of Terminal Ileal Biopsies".
  22. M Khalifehloo,M Mohammad,M Heydari (2017). Air and Water Environments.
  23. F Othman Investigating the effectiveness of seasonalization based on statistical parameters in.

Funding

No external funding was declared for this work.

Conflict of Interest

The authors declare no conflict of interest.

Ethical Approval

No ethics committee approval was required for this article type.

Data Availability

Not applicable for this article.

How to Cite This Article

Mohammad Javad Khosravi. 2019. \u201cThe Economic Development of Dam Construction Projects by Applying a Critical Chain Project Management\u201d. Global Journal of Research in Engineering - E: Civil & Structural GJRE-E Volume 19 (GJRE Volume 19 Issue E2): .

Download Citation

Journal Specifications

Crossref Journal DOI 10.17406/gjre

Print ISSN 0975-5861

e-ISSN 2249-4596

Keywords
Classification
GJRE-E Classification: FOR Code: 090599
Version of record

v1.2

Issue date

June 8, 2019

Language
en
Experiance in AR

Explore published articles in an immersive Augmented Reality environment. Our platform converts research papers into interactive 3D books, allowing readers to view and interact with content using AR and VR compatible devices.

Read in 3D

Your published article is automatically converted into a realistic 3D book. Flip through pages and read research papers in a more engaging and interactive format.

Article Matrices
Total Views: 2792
Total Downloads: 1244
2026 Trends
Related Research

Published Article

The dam construction industry in Iran has always been considered as one of the country’s most important industries due to the lack of rainfall. To accomplish this, we need to properly manage the dam construction process. Traditional algorithms, such as the Critical Paths Methods (CPM) and Program Evaluation and Review Technique (PERT) have been used since ancient times to plan and control most of the projects, including dam construction projects. With traditional methods of project management, a large percentage of time and resources are often lost due to reasons such as the lack of prioritization, student syndrome, and bad multi-tasking. The Critical Chain Project Management (CCPM) is a method for project planning, with emphasis on the resources needed to carry out the project. In this research, which was done on the Kahir reservoir, the CPM method was first used and then analyzed by CCPM method. Using resource dependency, identifying and embedding project buffers and leveling resources in this study reduced the implementation time of the project for 27 days

Our website is actively being updated, and changes may occur frequently. Please clear your browser cache if needed. For feedback or error reporting, please email [email protected]

Request Access

Please fill out the form below to request access to this research paper. Your request will be reviewed by the editorial or author team.
X

Quote and Order Details

Contact Person

Invoice Address

Notes or Comments

This is the heading

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

High-quality academic research articles on global topics and journals.

The Economic Development of Dam Construction Projects by Applying a Critical Chain Project Management

Mohammad Javad Khosravi
Mohammad Javad Khosravi Islamic Azad University, Tehran

Research Journals